Biodigester Sewage Treatment

Sewage Treatment Plants

Home About Us Contact Us

+44 (0)1278 786 104

Tel:

email:

The real alternative

Principle Certifications Resources FAQ Installation Products

Installation

Installation

  • Excavate a hole 300mm wider and 200mm deeper than the relevant unit.

  • Check the water table. If there is any chance of the water rising above the base of the unit then the Wett Ground method must be used.

  • Install 200mm base of sand, gravel, scalpings or concrete.

  • Place BIODIGESTER onto base, work ribs into base and check levels carefully.

  • Fill the BIODIGESTER with water.

  • If you have a high water table the Wet Ground anchors must be covered with at least 250mm of concrete to the minimum quantity specified by the data sheet.

  • Backfill with gravel or concrete as preferred.

sewage treatment install

How much concrete to cover the anchors?

T6       T12       T18       T24       T30       T36

3m       4m        5m       10m     12.5m    15m

3

3

3

3

3

3

For more detailed installation information, specifications and other information, contact us direct.

Installation is simple in areas of a high water table. Just cover the anchors with the quantity of concrete specified in the appropriate datasheet.